HMP Wormwood Scrubs D Wing Refurbishment

PMA delivered a full refurbishment to over 150 rooms at HMP Wormwood Scrubs.

PMA delivered a full refurbishment to over 150 rooms at HMP Wormwood Scrubs.

PMA were awarded the refurbishment of the D4 and D3 landings at HMP Wormwood Scrubs. These were completed over a period of 28 weeks consecutively. The works included the full refurbishment to 8 shower rooms, 22 offices and 128 cells including all landings and corridors, gates and mesh panelling. The works developed a bespoke metal panelling system to provide decency to the WC facilities as well as the replacement to outdated infrastructure and sanitaryware.