Between February 2021 and May 2021, we installed 64 Nr sleeper units at HMP Standford Hill for GFSL at a cost of £2.9 million.
Details:
As part of the project we:
Between February 2021 and April 2021, we installed 80 Nr sleeper units at HMP Ford for GFSL at a cost of £2.6 million.
Details:
We installed 80 permanent sleepers, 4 ambulant accessible sleepers, 2 single kitchens, 2 single laundries, and 2 single pin phones.
As part of the project we:
Between March 2020 and June 2020, we installed 2 Nr safety cells at HMP Wandsworth for GFSL at a cost of £210,000.
Details:
We altered and adapted the existing standard cells into compliant safer cells.
As part of the project we:
Between June 2020 and September 2020, we installed temporary accommodation portacabins at HMP East Sutton Park at a cost of £250,000.
Details:
In response to the Covid-19 outbreak the MoJ sourced and purchased a number of individual portacabins and asked us to place them in a temporary designated location. The idea was to provide isolation areas to help manage and contain the Covid outbreak there.
As part of the project we:
Between June 2020 and September 2020, we installed temporary accommodation portacabins at HMP The Verne at a cost of £189,000.
Details:
In response to the Covid-19 outbreak the MoJ sourced and purchased a number of individual portacabins and asked us to place them in a temporary designated location. The idea was to provide isolation areas to help manage and contain the Covid outbreak there.
As part of the project we:
Between June 2020 and September 2020, we installed temporary accommodation portacabins at HMP Huntercombe at a cost of £155,000.
Details:
In response to the Covid-19 outbreak the MoJ sourced and purchased a number of individual portacabins and asked us to place them in a temporary designated location. The idea was to provide isolation areas to help manage and contain the Covid outbreak there.
As part of the project we:
Between June 2020 and September 2020, we installed temporary accommodation portacabins at HMP Guys Marsh at a cost of £217,000.
Details:
In response to the Covid-19 outbreak the MoJ sourced and purchased a number of individual portacabins and asked us to place them in a temporary designated location. The idea was to provide isolation areas to help manage and contain the Covid outbreak there.
As part of the project we:
Between January and March 2020, we completed a health care dental project at HMP Birmingham at a cost of £210,000.
Details:
The project was a sensitive one and the work was carried out at weekends. We altered and adapted an existing office; converting the area into an NHS-compliant dentist in-establishment facility.
As part of the project we:
Between January and March 2020, we undertook an adapted equality cell conversion and holding room alteration at HMP Wormwood Scrubs at a cost of £138,000.
Details:
There was a tight deadline with this project and we were awarded it with five weeks to go until the year-end. It was successfully completed on time.
As part of the project we:
In December 2019, we adapted wing offices into healthcare areas at HMP Birmingham for AMEY PLC at a cost of £98,000.
Details:
We were contracted to alter and adapt a number of existing wing offices to convert them into healthcare and medicine dispensing areas. As the work was undertaken on a live wing, we also carried out weekend work to speed up the project.
As part of the project we:
Between May 2019 and October 2019, we undertook an extension to the CSU wing at HMP Birmingham for the MoJ at a cost of £350,000.
Details:
The work was undertaken in a live environment and included out of hours and weekend work. It involved installing security hoardings to facilitate the work.
As part of the project we:
Between March 2019 and May 2019, we undertook the refurbishment of a mess cafe at HMP Send for the MoJ at a cost of £124,000.
Details:
The area had been used previously as an officers’ social club and it was isolated, cleaned, and stripped before being refurbished.
As part of the project we:
Between August 2019 and September 2019, we undertook the reinstatement of Wing B at HMP Winchester for HMP at a cost of £150,000.
Details:
We were asked to go on-site to assess the general damage to the wing following a disturbance.
As part of the project we:
Between November 2019 and January 2020, we reinstated NOMS-approved secure and compliant security ceilings at HMP Wormwood Scrubs for GFSL at a cost of £68,000.
Details:
During a routine survey it was discovered that the ceilings were non-compliant and provided a security breach problem. We installed NOMS-approved secure and compliant ceilings out of hours to keep the area in operation.
Between October 2020 and January 2021, we undertook seg reinstatements work at HMP Wandsworth for GFSL at a cost of £70,000.
As part of the project we:
Between September 2020 and March 2021, we installed 5 Nr showers at HMP Wormwood Scrubs for GFSL at a cost of £220,000.
As part of the project we:
Between August 2018 and January 2019, we undertook 38 cell refurbishments at HMP Chelmsford for the MoJ at a cost of £300,000.
As part of the project we:
Between January 2020 and June 2020, we undertook 5 Nr shower refurbishments at HMP Wandsworth for GFSL at a cost of £300,000.
As part of the project we:
Between November 2018 and January 2019, we undertook the refurbishment of a high-spec shower at HMP Rochester for the MoJ at a cost of £89,000.
As part of the project we:
Between January 2020 and June 2020, we undertook 2 Nr shower refurbishments at HMP Wormwood Scrubs for GFSL at a cost of £110,000.
As part of the project we:
Between February 2019 and April 2019, we created 2 new shower rooms at HMP Brinsford for the MoJ at a cost of £125,000.
As part of the project we:
Between November 2018 and January 2019, we created a new equalities act compliant accessible shower at HMP Wandsworth for the MoJ at a cost of £45,000.
As part of the project we:
Between April 2020 and June 2020, we altered and adapted an existing wing at HMP/YOI Feltham for GFSL to make it suitable for use as an ESU wing at a cost of £159,000.
As part of the project we:
Between December 2018 and February 2019, we installed new specialist security gates at HMP Wormwood Scrubs for the MoJ at a cost of £30,000.
As part of the project we installed NOMs-approved security gates to the new visiting area. The work was undertaken out of hours.
Between April 2020 and June 2020, we installed legal safe booths at HMP/YOI Feltham for the provision of legal visits at a cost of £149,000
As part of the project we:
Between March 2020 and May 2020, we undertook a wing, shower, and servery refurbishment project at HMP Feltham at a cost of £148,000.
As part of the project we:
Between January 2020 and March 2020, we undertook an ESU unit refurbishment at HMYOI Feltham at a cost of £295,000.
As part of the project we:
Between December 2019 and March 2020, we completed legal and closed visits at HMYOI Feltham at a cost of £115,000.
The visits were undertaken out of hours and at weekends to keep the establishment’s areas live and operational.
The purpose of the project was to complete a new visiting area. We:
Between April 2019 and June 2019, we created 2 new showers at HMP Feltham for the MoJ at a cost of £107,000.
As part of the project we:
Between January 2020 and June 2020, we undertook the first phase of installing 5 new showers at HMP Wormword Scrubs at a cost of £610,000.
As part of the project we:
Between January 2020 and March 2020, we installed a D1 shower at HMP Whitemoor at a cost of £79,000.
As part of the project we:
Between June 2019 and August 2019, we created 2 new showers at HMP Wandsworth for GFSL at a cost of £115,000.
As part of the project we:
Between May 2019 and July 2019, we created 2 new showers at HMP Wormwood Scrubs for GFSL at a cost of £99,000.
As part of the project we:
Between July 2018 and December 2018, we undertook 104 cell wing refurbishments at HMP Wormwood Scrubs for the MoJ at a cost of £475,000.
As part of the project we: